Plugging and abandonment of the Römerberg 0 building in Speyer successfully completed
The consortium comprising Neptune Energy and Palatina GeoCon has completed the plugging and abandonment of all operational facilities, including the Römerberg 0 well on Nikolaus-von-Weis-Straße. The site has now been prepared for further use by the owner.
Work began in early June 2026. The project team permanently sealed the well using special cement and mechanical barriers. A winch approximately 45 metres high was in place on site for this purpose one last time for around a month. The backfilling was completed as early as July.
After that, the focus shifted to the infrastructure. The team removed the drilling pit and stripped back the existing asphalt surface. In total, the team moved 300 tonnes of concrete, 880 tonnes of asphalt and 2,200 tonnes of crushed stone on site.
“For us, plugging and abandonment are just as much a part of responsible raw material extraction as the safe operation of our wells. We only use sites and facilities for as long as we need them. Afterwards, we properly restore them and return the land to its owners,” says Horst Prei, Head of Production in Speyer at Neptune Energy.
Plugging and abandonment is therefore not an exceptional case, but part of the life cycle of raw material extraction.
Plugging and abandonment go hand in hand
The completion of the Römerberg 0 project does not mean the consortium is withdrawing from Speyer. Quite the contrary. Whilst Römerberg 0 involves the responsible decommissioning of infrastructure that is no longer required, the partners are simultaneously investing in the future of the Speyer site. The consortium is investing a sum in the hundreds of millions over the next few years.
“The plugging and abandonment of Römerberg 0 and the forthcoming investments highlight two aspects of our activities: we are taking responsibility for facilities that are no longer needed, whilst at the same time investing in modern infrastructure for the years to come,” says Horst Prei.
A well with a remarkable history
The history of oil production in Speyer began with the Römerberg 0 well. The well was drilled in 2003 in the search for geothermal energy. However, it transpired that no geothermal energy could be harnessed at this location. At a depth of around 2,350 metres, oil was unexpectedly discovered. The well thus confirmed the presence of an oil reservoir, although production never took place at this site. For subsequent production, the consortium established two so-called cluster sites on the outskirts of Speyer and has been producing oil there since 2008, which is transported to the oil refinery in Karlsruhe.
Over several years, the consortium investigated whether the Römerberg 0 well could still be used for other purposes from a technical perspective. Ultimately, the decision was taken to permanently plug the well and decommission the former central field station.
About Neptune Energy
Neptune Energy is one of Germany’s leading commodities companies. With over 135 years’ experience, we ensure a secure supply for industry and society. Our aim: Today we produce what counts tomorrow. Around 460 employees across many regions of Germany and at our head office in Hanover are committed to three key areas of activity
Base – Gas & Oil: safe and reliable production of domestic energy resources
Balance – plugging andabandonment: taking responsibility for the past and restoring nature
Boost – New Energy: actively shaping the future, for example with lithium from Germany
This is how we combine experience with progress. Neptune Energy’s revenue for the 2025 financial year stood at 332 million euros (IFRS). Total annual production of gas and oil amounted to 5.9 million barrels of oil equivalent (boe).