Navigation

Pruning work on the Brüchau plant

16. Februar 2026
BalanceSanierung Anlage Brüchau

Neptune Energy begins pruning work at the Brüchau mining waste disposal facility. Following the approval of the requested amendment to the final operating plan for incapsulation by the Saxony-Anhalt State Office for Geology and Mining (LAGB) in August 2025, these are the first visible measures at the facility.

The pruning work includes clearing the site of emerged vegetation, including mowing and shortening the reed belt. Due to the start of the breeding and setting season, the work must be completed before 1 March. The pruning serves to protect the existing population and is necessary at regular intervals.

Neptune Energy is still in the tendering process for the necessary engineering services. According to current planning, the contract is to be awarded in 2026 and implementation of the measures is to begin, although this is dependent on the outcome of the legal proceedings relating to BUND's complaint.

Detailed planning will then begin so that implementation of the first construction phase can probably start in 2027.

Questions & Answers

What happens in the first construction phase?

 

Once the award procedures have been completed, the landfill material will be pre-treated (conditioned) and relocated to temporary sections of the facility in construction phase 1 from 2027 at the earliest. Conditioning involves mixing and stabilising the material so that free water is bound in the predominantly sludgy landfill and the material becomes transportable. This is the prerequisite for all further processing steps, regardless of the subsequent procedure.

 


 

Are irreversible facts being created in the first construction phase?

 

For a permanently safe solution, it is necessary to condition the landfill. This does not create irreversible facts, but rather the prerequisites for making the material technically controllable and enabling subsequent processing and relocation. Conditioning ensures that the material retains an earth or soil-like structure without creating a concrete-like material state.

 


 

What condition is achieved by conditioning the material?

 

During conditioning, a limited quantity of cement-based conditioning agents is added to the landfill. The maximum amount added is up to 10 per cent by weight. This solidifies the material without creating a concrete-like solid.

After treatment, the conditioned material has an earth or soil-like structure, is transportable, no longer contains any free liquids and can be safely stacked in interim storage up to a minimum height of 3 metres.

Material from the preliminary tests (left: original material, right: the same material after conditioning)


You can find further information on our

Project page

Luftaufnahme des Geländes der Anlage Brüchau

About Neptune Energy

Neptune Energy is one of the leading raw materials companies in Germany. With over 135 years of experience, we secure supplies for industry and society. Our goal: Today we produce what counts tomorrow. Around 480 employees in many regions of Germany and at our headquarters in Hanover are involved in three key areas of activity

Base - Gas & Oil: safe and reliable production of domestic energy raw materials

Balance - Plugging and abandonment: taking responsibility for the past and restoring nature

Boost - New Energy: actively shaping the future, for example with lithium from Germany

This is how we combine experience with progress. Neptune Energy's revenue in the 2024 financial year was €440 million. The total annual production of gas and oil was 5.5 million barrels of oil equivalent (boe).

Your contact for queries

Maximilian Zindel

Corporate Communications


News from the company

The latest press releases, project updates and statements on our activities can be found here.

to the newsroom

Hannover/Steinitz
12.02.2026
16. Februar 2026
Plugging and abandonment of the Altensalzwedel 151 natural gas probe on the B71 motorway

Neptune Energy is backfilling the former AAZ 151 (Altensalzwedel 151/88) natural gas probe south of Mahlsdorf. The probe was drilled in 1988 and was in production until…

Neptune Energy Handlungsfeld Base Römerberg 10
Speyer
09.02.2026
16. Februar 2026
Römerberg 10 successfully put into production

Neptune Energy successfully drilled the Römerberg 10 well. The initial results show promising oil quantities. The partners are thus continuing their investments in the…

Georgsdorf
05.02.2026
16. Februar 2026
Neptune Energy starts gas production from the Adorf Z20 well in Lower Saxony

The new Adorf Z20 well south of Heideweg in Georgsdorf is now producing natural gas for the local grid.